Implementation
The following table shows the steps involved in a typical installation and the approximate duration of each task.
Although the smoothest implementations occur when the client manages the project and CNX performs the technical work and training, the client may elect to take on as much of the tasks as timing, budget and IT skills allow.
| Task | # of Days |
|---|---|
| Project Kick-Off Meeting | 1 |
| Technical Orientation | 1 |
| Install ATOMIC Modules | 1 |
| Create Test Environment | 1 |
| Install Pilot Hardware | 1 |
| Define Pilot Scenarios | 3 |
| Equipment Assessment | 1 |
| Project Team Training | 11 |
| ATOMIC Global Control | |
| ATOMIC SF Master Files | |
| ATOMIC SF Execution (includes MPS) | |
| ATOMIC RF Module | |
| ATOMIC UDS Module | |
| ATOMIC Label Management Module | |
| Load ATOMIC Master Files | 8 |
| Create Label Formats | 1 |
| Scenario Piloting | 33 |
| Programming Requirements | 5 |
| Make changes to User Ids | 1 |
| Equipment Installation | 2 |
| Readiness Assessment | 2 |
| End-User Training | 5 |
| Cutover | 3 |
| Post Implementation Review | 1 |