The following table shows the steps involved in a typical installation and the approximate duration of each task.

Although the smoothest implementations occur when the client manages the project and CNX performs the technical work and training, the client may elect to take on as much of the tasks as timing, budget and IT skills allow.

Task # of Days
Project Kick-Off Meeting 1
Technical Orientation 1
Install ATOMIC Modules 1
Create Test Environment 1
Install Pilot Hardware 1
Define Pilot Scenarios 3
Equipment Assessment 1
Project Team Training 11
ATOMIC Global Control
ATOMIC SF Master Files
ATOMIC SF Execution (includes MPS)
ATOMIC RF Module
ATOMIC UDS Module
ATOMIC Label Management Module
Load ATOMIC Master Files 8
Create Label Formats 1
Scenario Piloting 33
Programming Requirements 5
Make changes to User Ids 1
Equipment Installation 2
Readiness Assessment 2
End-User Training 5
Cutover 3
Post Implementation Review 1